How to Use This Book
This 2010 National Plumbing & HVAC Estimator is a guide to
estimating labor and material costs for plumbing, heating,
ventilating and air conditioning systems in residential, commercial
and industrial buildings.
Inside the back cover of this book you'll find an envelope with a
compact disk. The disk has National Estimator, an easy to-use
estimating program with all the cost estimates in this book. Insert
the CD in your computer and wait a few seconds. Installation should
begin automatically. (If not, click Start, Settings, Control Panel,
doubleclick Add/Remove Programs and Install.) Select Show Me from
the installation menu and Dan will show you how to use National
Estimator. When Show Me is complete, select Install Program. When
the National Estimator program has been installed, click Help on the
menu bar, click Contents, click Print all Topics, click File and
click Print Topic to print a 40-page instruction manual for National
Estimator.
Costs in This Manual will apply within a few percent on a
wide variety of projects. Using the information given on the pages
that follow will explain how to use these costs and suggest
procedures to follow when compiling estimates. Reading the remainder
of this section will help you produce more reliable estimates for
plumbing and HVAC work.
Manhour Estimates in This Book will be accurate for some jobs
and inaccurate for others. No manhour estimate fits all jobs because
every construction project is unique. Expect installation times to
vary widely from job to job, from crew to crew, and even for the
same crew from day to day.
There's no way to eliminate all errors when making man hour
estimates. But you can minimize the risk of a major error by:
1. Understanding what's included in the manhour estimates in this
book, and
2. Adjusting the man hour estimates in this book for unusual job
conditions.
The Craft@Hrs Column. Manhour estimates in this book are
listed in the column headed Craft@Hrs. For example, on page
19 you'll see an estimate for installing a 6 gallon hot water
heater. In the Craft@Hrs column opposite 6 gallon you'll see:
P1 @.500
To the left of the @ symbol you see an abbreviation for the
recommended work crew.
Page 7 shows the wage rates and craft codes used in this book.
To the right of the @ symbol you see a number. The number is the
estimated manhours (not crew hours) required to install each unit of
material listed. In the case of a 6 gallon hot water heater, P1 @
.500 means that .500 manhours are required to install 1 hot water
heater.
Costs in the Labor $ Column are based on manhour estimates in
the Craft@Hrs column. Multiply the manhour estimate by the . assumed
hourly labor cost to find the installation cost in the Labor $
column. For example, .500 manhours times $35.07 (the average wage
for crew P1) is $17.54.
Monthly price updates on the Web are free and automatic all
during 2010. You'll be prompted when it's time to collect the next
update. A connection to the Web is required.
Manhour Estimates include all productive labor normally
associated with installing the materials described. These estimates
assume normal conditions: experienced craftsmen working on
reasonably well planned and managed new construction with fair to
good productivity. Labor estimates also assume that materials are
standard grade, appropriate tools are on hand, work done by other
crafts is adequate, layout and installation are relatively
uncomplicated, and working conditions don't slow progress.
All manhour estimates include tasks such as:
Unloading and storing construction materials, tools and
equipment on site.
Working no more than two floors above or below ground level. .
Working no more than 10 feet above an uncluttered floor.
Normal time lost due to work breaks.
Moving tools and equipment from a storage area or truck not more
than 200 feet from the work area.
Returning tools and equipment to the storage area or truck at
the end of the day.
Planning and discussing the work to be performed.
Normal handling, measuring, cutting and fitting.
Regular cleanup of construction debris.
Infrequent correction or repairs required because of faulty
installation.
If the work you're estimating won't be done under these conditions,
you need to apply a correction factor to adjust the manhour
estimates in this book to fit your job.
Applying Correction Factors. Analyze your job carefully to
determine whether a labor correction factor is needed. Failure to
consider job conditions is probably the most common reason for
inaccurate estimates.
Use one or more of the recommended correction factors in Table 1 to
adjust for unusual job conditions. To make the adjustment, multiply
the man hour estimate by the appropriate conversion factor. On some
jobs, several correction factors may be needed. A correction factor
less than 1.00 means that favorable working conditions will reduce
the man hours required.
Supervision Expense to the installing contractor is not
included in the labor cost. The cost of supervision and
nonproductive labor varies widely from job to job. Calculate the
cost of supervision and non-productive labor and add this to the
estimate.
Hourly Labor Costs also vary from job to job. This book
assumes an average man hour labor cost of $40.47 for plumbers and
$39.70 for sheet metal workers. If these hourly labor costs are not
accurate for your jobs, adjust the labor costs up or down by an
appropriate percentage. Instructions on the next page explains how
to make these adjustments. If you're using the National Estimator
disk, it's easy to set your own wage rates.
Hourly labor costs in this book include the basic wage, fringe
benefits, the employer's contribution to welfare, pension, vacation
and apprentice funds, and all tax and insurance charges based on
wages. Table 2 at the top of the next page shows how hourly labor
costs in this book were calculated. It's important that you
understand what's included in the figures in each of the six columns
in Table 2. Here's an explanation:
Column 1, the base wage per hour, is the craftsman's hourly
wage. These figures are representative of what many contractors are
paying plumbers, sheet metal workers and helpers in 2010.
Column 2, taxable fringe benefits, includes vacation pay,
sick leave and other taxable benefits. These fringe benefits average
about 5.15% of the base wage for many plumbing and HVAC contractors.
This benefit is in addition to the base wage.
| Condition |
Correction
Factor |
|
Work in large open areas, no partitions |
.85 |
| Prefabrication under ideal conditions, bench work |
.90 |
| Large quantities of repetitive work |
.90 |
| Very capable tradesmen |
.95 |
| Work 300' from storage area |
1.03 |
| Work 400' from storage area |
1.05 |
| Work 500' from storage area |
1.07 |
| Work on 3rd through 5th floors |
1.05 |
| Work on 6th through 9th floors |
1.10 |
| Work on 10th through 13th floors |
1.15 |
| Work on 14th through 17th floors |
1.20 |
| Work on 18th through 21st floors |
1.25 |
| Work over 21 floors |
1.35 |
| Work in cramped shafts |
1.30 |
| Work in commercial kitchens |
1.10 |
| Work above a sloped floor |
1.25 |
| Work in attic space |
1.50 |
| Work in crawl space |
1.20 |
| Work in a congested equipment room |
1.20 |
| Work 15' above floor level |
1.10 |
| Work 20' above floor level |
1.20 |
| Work 25' above floor level |
1.30 |
| Work 30' above floor level |
1.40 |
|
Work 35' to 40' above floor level |
1.50 |
| Table 1 Recommended Correction Factors |
|
Column 3, insurance and employer-paid taxes in percent,
shows the insurance and tax rate for the craft workers. The cost of
insurance in this column includes workers' compensation and
contractor's casualty and liability coverage. Insurance rates vary
widely from state to state and depend on a contractor's loss
experience. Note that taxes and insurance increase the hourly labor
cost by approximately 30%. There is no legal way to avoid these
costs.
Column 4, insurance and employer taxes in dollars, shows the
hourly cost of taxes and insurance.
Insurance and taxes are paid on the costs in both columns 1 and 2.
Column 5, non-taxable fringe benefits, includes employer paid
non-taxable benefits such as medical coverage and tax-deferred
pension and profit sharing plans. These fringe benefits average
4.55% of the base wage for many plumbing and HVAC contractors.
|
Column Number |
1 |
2 |
3 |
4 |
5 |
6 |
|
Craft |
Base Wage
per hour |
Taxable
fringe
benefits (at
5.15% of
base wage) |
Insurance
and
employer
taxes (%) |
Insurance
and
employer
taxes ($) |
Non-taxable
fringe
benefits (at
4.55% of
base wage) |
Total hourly
cost used in
this book |
| Laborer |
20.55 |
1.06 |
32.93% |
7.12 |
0.94 |
29.67 |
| Plumber |
29.88 |
1.54 |
24.47% |
7.69 |
1.36 |
40.47 |
| Sheet Metal Worker |
28.92 |
1.49 |
26.21% |
7.97 |
1.32 |
39.70 |
| Operating Engineer |
29.35 |
1.51 |
25.42% |
7.84 |
1.34 |
40.04 |
| Sprinkler Fitter |
29.35 |
1.51 |
25.28% |
7.80 |
1.34 |
40.00 |
| Electrician |
29.27 |
1.51 |
20.04% |
6.17 |
1.33 |
38.28 |
|
Craft Code |
Crew Composition |
Average Hourly Cost
per Manhour |
| ER |
4 building plumbers, 2 building laborers, 1 operating
engineer |
37.32 |
| SN |
4 building sheet metal workers, 2 building laborers, 1
operating engineer
|
36.88 |
| P1 |
1 building plumber and 1 building laborer |
35.07 |
| ST |
1 sprinkler fitter |
40.00 |
| SK |
4 sprinkler fitters, 2 building laborers, 1 operating
engineer |
37.05 |
| SL |
1 sprinkler fitter and 1 laborer |
34.84 |
| S2 |
1 building sheet metal worker, 1 building laborer |
34.69 |
|
BE |
1 electrician |
38.28 |
| Table 2 labor Costs Used in This Book |
|
The employer pays no taxes or insurance on these benefits.
Column 6, the total hourly cost in dollars, is the sum of
columns 1, 2, 4, and 5. The labor costs in Column 6 were used to
compute costs in the Labor $ column of this book.
Adjusting Costs in the Labor $ Column. The hourly labor costs
used in this book may apply within a few percent on many of your
jobs. But wage rates may be much higher or lower in some areas. If
the hourly costs shown in Column 6 of Table 2 are not accurate for
your work, adjust labor costs to fit your jobs.
For example, suppose your hourly labor costs are as follows:
Plumber $19.00
Laborer $16.00
Total hourly crew cost $35.00
Your average cost per manhour would be $17.50 ($35.00 per crew hour
divided by 2 because this is a crew of two).
A labor cost of $17.50 is about 50% of the $35.07 labor cost used
for crew P1. Multiply costs in the Labor $ column by .50 to find
your estimated cost.
For example, notice on page 19 that the labor cost for installing a
6 gallon hot water heater is $17.50 each. If installed by your
plumbing crew working at an average cost of $17.50 per manhour, your
estimated cost would be 50% of $17.50 or $8.75 per heater.
Adjusting the labor costs in this book will make your estimates much
more accurate. Making adjustments to labor costs is both quick and
easy if you use the National Estimator disk.
Equipment Cost will vary according to need and application.
It typically is $110 per hour for a 10-ton hydraulic truck-mounted
crane.
Material Costs in this manual are intended to reflect what
medium- to low-volume contractors will be paying in 2010 after
applying normal discounts. These costs include charges for delivery
to within 25 to 30 miles of the supplier.
Overhead and Profit for the installing contractor are not
included in the costs in this manual unless specifically identified
in the text. Markup can vary widely with local economic conditions,
competition and the installing contractor's operating expenses. Add
the "markup that's appropriate for your company, the job and the
competitive environment.
How Accurate Are These Figures? As accurate as possible
considering that the editors don't know your material suppliers,
haven't seen the plans or specifications, don't know what building
code applies or where the job is, had to project material costs at
least six months into the future, and had no record of how much work
the crew that will be assigned to the job can handle.
You wouldn't bid a job under those conditions. And I don't claim
that all plumbing and HVAC work is done at these prices.
Estimating Is an Art, not a science. There is no one price
that applies on all jobs. On many jobs the range between high and
low bid will be 10% or more.
There's room for legitimate disagreement on what the correct costs
are, even when complete plans and specifications are available, the
date and site are established, and labor and material costs are
identical for all bidders.
No estimate fits all jobs. Good estimates are custom made for a
particular project and a single contractor through judgment,
analysis and experience. This book is not intended as a substitute
for judgment, analysis and sound estimating practice. It's an aid in
developing an informed opinion of cost, not an answer book.
Additional Costs to Consider
Here's a checklist of additional costs to consider before submitting
any bid.
1. Sales taxes
2. Mobilization costs
3. Payment and performance bond costs
4. Permits and fees
5. Storage container rental costs
6. Utility costs
7. Tool costs
8. Callback costs during warranty period
9. Demobilization costs
Exclusions and Clarifications
Neither the job specifications nor the contract may identify exactly
what work should be included in the plumbing and HVAC bid.
Obviously, you have to identify what work is included in the job.
The most efficient way to define the scope of the work is to prepare
a list of tasks not normally performed by your company and attach
that list to each bid submitted. Here's a good list of work that
should be excluded from your bid.
Your Bid Should Exclude
Final cleaning of plumbing fixtures
Backings for plumbing fixtures
Toilet room accessories
Electrical work, including motor starters
Electrical wiring and conduit over 100 volts
Temporary utilities
Painting, priming and surface preparation
Structural cutting, patching or repairing
Fire protection and landscape sprinklers
Equipment supports
Surveying and layout of control lines
Removal or stockpiling of excess soil
Concrete work, including forming and rebar
Setting of equipment furnished by others
Equipment, unless shown, and personnel hoisting
Wall and floor blockouts
Pitch pockets
The costs of performance or payment bonds
Site utilities
Asbestos removal or disposal
Contaminated soil removal or disposal
Major increases in copper material prices
Fire dampers not shown on the plans
Your Bid Should Include
Trash sweep-up only. Others haul it away
Site utilities from building to property line only
Piping to 5 feet outside the building only
Plumbing & HVAC permits for your work only
Beware of Price Changes
There's no way to be sure what prices will be in three to six
months. All labor, equipment, material and subcontract prices in a
bid should be based on costs anticipated when the project is
expected to be built, not when the estimate is compiled. That
presents a problem. Except for the installation of underground
utilities, most plumbing and HVAC work is done six months to a year
after the bid is submitted. When possible, get price protection in
writing from your suppliers and subcontractors. If your suppliers
and subs won't guarantee prices, include an escalation allowance in
your bid to cover anticipated price increases.
Material Pricing Conditions
All equipment and material prices quoted by your vendors will be
conditional. They usually don't include sales tax and are subject to
specific payment and shipping terms. Every estimator should
understand the meaning of common shipping terms. They define who
pays the freight and who has responsibility for processing
freight-damage claims. Here's a summary of important conditions you
should understand.
F.O.B. Factory (Free On Board at the Factory): Title passes
to the buyer when the goods are delivered by the seller to the
freight carrier. The buyer pays the freight and is responsible for
freight-damage claims.
F.O.B. Factory F.F.A. (Free On Board at the Factory, Full
Freight Allowed): The title passes to the buyer when the goods are
delivered by the seller to the freight carrier. The seller pays the
freight charges, but the buyer is responsible for freight-damage
claims.
F.O.B. (city of destination) (Free On Board to your city):
The title passes to the buyer when the goods are delivered by the
seller to the freight terminal in the city, or nearest city, of
destination. The seller pays the freight and is responsible for
freight-damage claims to the terminal. The buyer pays the freight
charge and is responsible for freight-damage claims from the
terminal to the final destination.
F.O.B. Job Site (Free On Board at job site, or contractor's
shop): The title passes to the buyer when the goods are delivered to
the job site (or shop). The seller pays the freight and is
responsible for freight-damage claims.
F.A.S. Port [of a specific city] (Free Alongside Ship at the
nearest port): The title passes to the buyer when goods are
delivered to the ship dock or port terminal.
The seller pays the freight and is responsible for freight-damage
claims to the ship dock or port terminal only. The buyer pays the
freight and is responsible for freight-damage claims from the ship
dock or port terminal to the designated delivery point. Obviously,
it's to your advantage to instruct all vendors to quote costs F.O.B.
the job site or your shop.
Reducing Costs
Most construction specifications allow the use of alternative
equipment and materials. It's the estimator's responsibility to
select the most cost-effective products. Research and compare your
costs before making any decisions. Avoid selecting any material or
equipment simply because that's what you've always done.
Don't recommend plastic products such as ABS, PVC, or polypropylene
pipe or corrugated flexible ducts until you've checked local code
requirements. Most building codes prohibit use of these materials
inside public buildings such as schools, care centers and hospitals.
It's wise to select 100% factory-packaged equipment.
Beware of equipment labeled "Some assembly required" Field labor
costs for mounting loose coils, motors and similar equipment are
very high.
Value Engineering
Let's suppose you've submitted a combined plumbing and HVAC bid for
$233,000. Your cutthroat competitor put in a bid at $4,000 less,
$229,000. Obviously there's no way you're going to get the job.
Right?
Not so fast! Maybe value engineering can help you win that contract
- while fattening your profit margin.
Suppose the proposal you submitted had two parts. Part I is the bid
for $233,000, based entirely on job plans and specs, just the way
they were written. But appended to your proposal is Part II, a list
of suggestions for saving money without sacrificing any of the
capacity or quality designed into the system. Here's an example of
what might be in Part II:
1. Deduct for providing pipe hanger spacings per UPC in lieu of
specified spacings: $1,750.00
2. Deduct for reducing heating hot water pipe sizes by using 40
degrees F Delta T in lieu of specified 20 degrees F Delta T:
$4,600.00
3. Deduct for providing pressure/temperature taps at air handling
units, pumps and chillers in lieu of specified thermometers and
pressure gauges: $875.00
4. Deduct for eliminating water treatment in closed piping systems:
$1,800.00
5. Deduct for piping chilled and heating hot water pumps in parallel
in lieu of providing 100% standby pumps: $2,900.00
Total deductions: $11,925.00
Adopting these suggestions would make you low bidder by nearly
$8,000. A saving like that will be tempting to most owners,
especially if the owner understands that your suggestions result in
a system that is every bit as good and maybe better than the system
as originally designed.
You're not offering to undercut the competition. Far from it. You're
using knowledge and experience to create better value for the owner.
That's called value engineering and it's likely to win the respect
of nearly all cost-conscious owners.
Notice that reducing costs is only part of what value engineering is
all about. You don't cut costs at the expense of system quality,
integrity, capacity or performance.
Don't waste your time, and your client's, by offering to substitute
cheaper or lower-quality fixtures or equipment. Any cutthroat
contractor with a price list can do that. Recommend the use of
inferior materials and you'll be associated with the inferior goods
you promote. Some owners consider even the suggestion to be
insulting.
The recommendations you make (like most of those in the example)
will require design changes. You can expect to be examined (or even
challenged) on these points. Be ready to explain and defend each of
your suggestions. Convince the client (or the design engineer) that
your ideas are based on sound engineering principles and you're well
on the way to winning the owner's confidence and the contract.
Now, let's go back to the list and see how we might justify the five
value engineering recommendations.
1. Pipe Hanger Spacing. The pipe hanger spacings recommended
in the Uniform Plumbing Code (UPC) are calculated by experienced,
professional structural engineers. The safety factors used in these
calculations are very conservative. They've been widely used for
many years and have proved to be more than adequate. There's no need
for more hangers than the UPC requires.
2. Changing HHW Delta T. In hydronic heating systems, heat
measured in Btus is pumped to terminal units. The proposed change of
the Delta T, from 20 degrees F to 40 degrees F, has no effect
whatsoever on how many Btus the system delivers. You're not changing
anything but the volume of water being pumped. At lower volume
levels, the size of the pump, the pipe and the pipe insulation can
all be reduced. Not one of these changes will affect the system's
ability to transmit heat. Furthermore, operating costs will also
drop, since less pump horsepower will be needed to run the smaller
pump.
3. Thermometers/Pressure Gauges. Thermometers and pressure
gauges installed on or near vibrating machinery have a very short
life expectancy. Gauges quickly lose accuracy under harsh
conditions. Readings will become less and less reliable.
That's potentially dangerous. You can avoid this problem by using
insertion-type pressure/temperature taps instead. Store these
sensitive gauges in a desk drawer or a tool crib when not in use.
Safely stored, they're protected from damage. They'll give accurate
readings longer and won't need to be replaced as often. And they're
simple to use. Just insert a gauge in one of the conveniently
located taps. Make the reading, then remove the gauge and put it
away.
4. Water Treatment. ITT Bell & Gossett has done studies on
corrosion in closed hydronic systems that have a make-up water rate
of no more than 5% per year. These studies show that corrosion
virtually stops when entrained air is either removed or depleted. No
water treatment is needed in this closed system.
5. 100% Standby Pumps. Two pumps piped and operated in
parallel are more economical. Even if one pump fails, the other pump
can maintain delivery at 75 to 80% of the designed flow rate. That's
usually adequate for emergency operation.
These cost-saving ideas are small, but could tip the balance in your
favor. I hope they demonstrate the potential that value engineering
has when bidding jobs. Any time you're compiling an estimate, keep
an eye out for ways to save money or reduce the owner's cost. Jot a
note to yourself about each potential saving you identify. Before
submitting the bid, make a list of your alternate suggestions. Maybe
best of all, markup on your value engineering suggestions can be
higher than your normal markup. If value engineering can cut costs
by $10,000, maybe as much as $4,000 of that should end up in your
pocket!
Value Engineering: Surplus Materials
Value engineering doesn't begin and end with job plans and specs.
Value engineering means getting the most value at the least cost, no
matter whether it's value to the owner or value to the contractor.
Smart mechanical contractors learn to build extra value into their
jobs by controlling shrinkage of materials. Nearly every significant
plumbing and HVAC job ends with at least some surplus material on
hand. Material left over when the job is done tends to be discarded
as waste or hauled off the job in the back of a truck that doesn't
have your company name on the door. And why not? It's surplus - not
needed. The owner didn't need it. So now it's up for grabs.
Not quite. Let's consider who actually owns that surplus material.
When your company has been paid, every piece of material your crew
installed belongs to the building owner. But what about those
fittings, hangers and valves delivered to the job site but never
actually used? Almost certainly, those materials were included in
your bid. So aren't they the property of the owner? Not in my
opinion. The owner contracted for a mechanical system and
(presumably) has one. Unless it's a cost-plus job or a labor-only
job, the owner didn't buy materials delivered to the job site. The
owner bought a mechanical system and has one - completely separate
and apart from any surplus materials. In my mind, the property owner
has no more claim to left-over materials than the same owner would
have claim to labor hours not expended or equipment not used on the
same job.
Unless there's some provision in your contract to the contrary,
surplus material belongs to the installing contractor. But your
right to that material and the chance of actually getting it back to
your shop are two very different propositions. I see recovery of
surplus material as a training issue. As a matter of company policy,
make it clear to your crews that surplus material belongs to your
company. The supervisor on every job should be accountable for
recovery of excess material. Every significant job will have at
least some surplus. Accounting for that surplus should be part of
your routine close-out procedure.
Fortunately, it's not difficult. I'll explain.
Control of surplus materials begins with a good checklist, or form.
I recommend the Materials, Equipment and Tool form, "MET" for short.
A blank MET form appears following this section. Your MET should
show both what's delivered to the job site (material, equipment and
tools) and surplus & drops returned to your shop at project
close-out. A MET ensures that the estimator, the shop inventory
manager and your field supervisor are on the same page. Your MET
establishes accountability. Nothing falls through the cracks. Job
input equals job output plus returns. Everything delivered to the
job and not expended should be returned to your shop.
Here's how it works:
1. Based on the estimate that won you the job, the items needed are
purchased for the job and staged for delivery to the job site.
2. As materials, equipment and tools are delivered to the job site,
your supervisor completes the first three columns of the MET form:
Description, Quantity and Date.
3. As work is completed, the same supervisor completes the four
columns under Returned to Inventory: Quantity Returned, Date, Status
Code and Value. The status code will be either "RS" (Returned and
Salvaged) or "RN" (Returned New).
4. Back at your shop, both RS and RN materials should be restored to
inventory.
5. If your company has an inventory manager, have that manager
assign the return value to each item returned. If you're using
QuickBooks Pro, the "Adjust Inventory" feature can handle this task
quite easily. Add two new categories under "Inventory Stock on Hand
by Vendor:' The first new category is Returned Salvage. The second
is Returned New. Be sure the value of RS materials includes the cost
of any reconditioning done to restore salvaged materials (such as
pumps and boilers) to serviceable condition.
6. Comparing MET deployed to the job site with MET returned to
inventory yields MET actually used on the job. That's a very
important number to every plumbing and HVAC estimator. Be sure
actual usage gets entered on the Project Summary form.
7. When the take-off on your next estimate is complete, compare that
materials list with a summary of RS and RN materials on hand from
prior jobs.
8. Evaluate which returned materials can be redeployed on the new
job.
9. It's a management decision to either (1) charge the new job for
the cost of RS and RN materials already on hand, or (2) consider
materials on hand as "free" and a competitive advantage in winning
the new bid. Either way, RN and RS materials are an asset to your
company.
Plumbing and HVAC materials are expensive. Every mechanical
contractor has an interest in MET tracking. Everyone in your company
should be aware of the need for good materials management. Used
correctly, the MET form in this book can help engineer more value
into your jobs.
Maximizing the Value of Old Estimates
There should be two profits in every job. The first is money in the
bank - a return on time and expenses.
The second is what you learn from the job - primarily by comparing
the estimate you made with what turns out to be your actual cost. On
some jobs, the value of lessons learned may outweigh net revenue.
Every plumbing and HVAC contractor has marginal jobs. That's normal.
What shouldn't be normal is repeating mistakes. The best way to
avoid trouble in your future is to keep track of your past. Keeping
old estimates available for reference can help prevent errors on new
estimates.
As your file of completed estimates grows, organization becomes more
important. You need an easy way to find similar projects with the
same components and comparable scope of work. If your estimating
file is in QuickBooks Pro, searching by keyword may be enough.
Otherwise, I recommend creating a short summary for each completed
job, and an index that references all summaries available for
comparison. You'll find a blank Project Summary form at the end of
this section. To make reference easier, create an index by type of
job and equipment used. You may choose to use an alphabetical index
based on client name or project 10.
How to complete the Project Summary form is obvious. The many ways
to use this form may not be so obvious, so here are a few pointers.
1. Use your index of Project Summary forms to find completed jobs
most similar to the job you're bidding. Believe it or not, Project
Summary forms with the widest margin of error will be most useful.
Ask yourself: Who worked on those projects? Who was the field
superintendent? Who were the vendors? Did the errors result from
poor estimating or the poor performance of vendors, supervisors or
crews? The most common estimating errors occur when (a) inspecting
the job site, (b) examining the plans or (c) reading the
specifications. What did you miss and why? Look for pitfalls to
avoid in the job now being estimated. Identify the biggest two or
three mistakes made when bidding that job. Make a notation about
each on the Project Summary form.
2. Now look at your bid for the current job. Which mistakes made on
a prior job might you expect on this job? Concentrate on the big
three oversights to avoid: Inspecting the job site; examining the
plans; and reading the specifications.
3. Unless there's a major error in take-off, your estimate of
material costs should be within about 5 percent of the actual costs
of materials. However, it's common for labor cost estimates to vary
20 percent or more from actual labor costs. This is precisely where
data from old jobs comes in handy. If your Project Summary files
show that some project types are consistent money-losers, either
shift your company's focus to another class of work, factor more
contingency into your bids, or find some way to wring inefficiencies
out of the labor component. Poor staging, delivery and retrieval
procedures drag down labor productivity on any job. .
4. Use your file of Project Summary forms to spot any common thread
that runs through either money-making jobs or money-losing jobs. For
example, if the names of certain subcontractors or vendors are
prominent on low-margin jobs, maybe there's a relationship between
your profit margin and choice of subs and suppliers. Even the best
and most reliable vendors can become complacent if not challenged
occasionally.
5. Project Summary forms should note changes and extras identified
after the contract was signed both for which your company was paid
and changes done without additional compensation. Projects with
changes and extras that exceed about 4 percent of the contract price
deserve special scrutiny. Jobs with changes beyond about 4 percent
aren't good for business, at least in my opinion. Nearly all changes
have a negative impact on your job schedule and require a
disproportionate investment of management resources. Too many
changes can antagonize the owner and design staff, even if they were
responsible for the altered plans. You may know of a mechanical
contractor with a reputation for capitalizing on change orders. But
I've rarely seen a job plagued with changes that turned into a
money-maker for anyone - except the attorneys. Your file of Project
Summary forms will show job types that carry change order risk.
Before finalizing and submitting any bid, consider whether the job
will get mired in disputes over changes and extras. If similar jobs
have ended on the courthouse steps, factor that risk into your
estimate.
Utility of a Project Summary forms file is limited only by your
ingenuity. The important point is to keep and organize the source of
your second profit available on every job. What you learn can be
more valuable than what you earn.
The Estimating Procedure
Every plumbing and HVAC estimator works under deadline pressure.
You'll seldom have the luxury of spending as much time as you would
like on an estimate. Estimators who aren't organized waste valuable
time and tend to make careless errors. Try to be well organized and
consistent in your approach to estimating. For most projects, I
recommend that you follow the procedures listed below and in the
order listed:
1. Get a second set of project drawings and specifications for use
by your suppliers and subcontractors. Remember that your subs and
suppliers need access to the plans and specs and time to prepare
their quotes.
2. Study the plans and specs carefully. Highlight important items.
Make a list of specific tasks that require labor unit correction
factors. The estimate is never complete until you're totally
familiar with the project and the applicable construction codes.
3. Get the general contractor or owner to identify the proposed
construction schedule and subcontractor lay-down (storage) area.
Work schedule and site conditions always affect your costs.
4. Contact all potential suppliers and subcontractors as early as
possible. Set a time when each can come to your office to make their
take-offs from the spare set of contract documents.
When this important preliminary work is done, or in progress, it's
time to begin your detailed take-off.
Guidelines for Good Estimating
You can compile estimates on a legal pad, a printed
estimating form or on a computer. Regardless of the method, these
guidelines will apply:
List Each Cost Separately on your take-off sheet.
Don't combine system estimates, even if the materials are the same
type. A combined system estimate may have to be completely redone if
materials for one system are changed at a later date. Use the
Estimate Detail Sheet on page 16 if you don't already have a good
material take-off form.
Use Engineer's Identification Numbers when listing equipment.
The word pump without any other description is ambiguous when there
are several pumps included in the project.
Don't Forget Labor Adjustment factors if your labor costs are
significantly higher or lower than the costs used in this book. See
instructions on page 7 for adjusting labor costs.
Use Colored Pencils or highlighters to mark the items you've
taken off and listed. Use a different color for each piping or
ducting system.
Log Telephone Quotes and other important phone conversations
on a telephone quote form. See the sample on page 18.
Project Estimated Costs for labor, material and equipment to
the time when the work is expected to be done, not when the job is
being estimated.
The only good estimate is a complete estimate.
You've probably heard this saying, "He who makes the most mistakes
is likely to be low bidder, and live to regret it."
Preparing the Proposal
It's both common courtesy and good business practice to deliver an
unpriced copy of your bid or proposal letter to the general
contractor three or four days before the bid deadline date. This
gives the contractor time to study your proposal and obtain
alternate pricing for items you may have excluded. To avoid
misunderstandings, make sure your proposals include, as a minimum,
the following elements:
1. The complete name and address of the proposed project.
2. Specification title and issue date.
3. A complete listing of drawings and their issue or revision date.
4. A complete list of addenda and their dates of issue.
5. A list of specification section numbers covered by your proposal.
6. A list of exclusions, clarifications and assumptions.
Your final bid can be phoned in or sent by fax, but it should reach
the general contractor or owner no more than five or ten minutes
before the bid deadline. Prices submitted too early may have to be
revised because of last-minute price changes by subcontractors or
suppliers.
- We will stop the chapter sample here on page 13. The
remaining 6 pages of this chapter consist of a "MET" Worksheet,
Project Summary form, Estimate Detail Sheet, Quotation Sheet,
and Record of Telephone Conversation form.
Softcover - 417 Pages
8-1/2 x 11 in.
>>
Introduction / Contents
Related:
more Cost
Guides
more Plumbing Related
more HVAC/R Related
HVAC
Exam Prep
Welding Related
HVAC Tools
Electrical Related
Electrical Exam Prep
2008 NEC and Related
2005 NEC and Related
Electrical Theory
Electrical Calculations
Electrical
Estimating
Electrician's Tools
Electrical Supplies
9781572181809
| 9781572182141
|